THE steelwork installation is set to begin on the replacement footway at Otley Bridge.
The work, which starts the Saturday (September 27) is due take around two to three weeks to complete and marks the start of the final phase of works in replacing the main footway.
This phase of works sees Otley Bridge night closures from 8pm to 5.30am between September 27 and October 18, to enable the installation of steel works. A signed diversion route is in place.
These works involve a 450-tonne crane arriving on Saturday and lifting the steelwork in place from Tittybottle Park.
The team then managed to avoid the need for full weekend closures of Otley Bridge as programmed before.
Now only two weekends of lane closures are necessary towards the end of October for utility companies to divert services back over the new footway.
Despite recent challenges with high river levels, the reinforcement and recasting of the cantilevers to meet current standards was completed last night.
The team discovered during demolition that repairs are needed to the pilasters on Otley Bridge.
This is unforeseen and could add approximately three weeks to the programme.
These structural improvements are essential to ensure the long-term safety and durability of the new footway.
Whie some disturbance and inconvenience is inevitable, Leeds City Council will do its best to minimise disruption.
Councillor Jonathan Pryor, Leeds City Council’s deputy leader and executive member for economy, transport, and sustainable development, said: “For around two to three weeks from September 27, the works will start on steelwork installation for the replacement footway.
“Lifting the steel components into place, is like fitting the final jigsaw pieces together and when complete will show the full extent of the new footway.
“After this, repairs will then take place to the pilasters on Otley Bridge.
“The project is making major progress despite some complex, challenging conditions and stormy weather, as we get closer to completing.
“Despite some disruption we will continue our best efforts to minimise this as much as possible.
“However, I know that it will still be inconvenient for people, and I would like to thank everyone for their understanding and patience, as we carry out this final installation.”