A TEMPORARY walkway over the River Wharfe has opened, allowing for works to begin on an 800-year-old bridge.
The Otley temporary footbridge opened to the public today after its setup began in March with the first section craned into place in April.
It marks a milestone in the project to replace the main footway on Otley Bridge.
The next phase of works involves the bridge being closed over two nights between May 27 and 29, from 8pm to 5am, to enable the installation of concrete barriers and white lining works.
A third night, May 29, is a contingency closure subject to the weather.
The Otley temporary footbridge (Image: Leeds City Council) It comes after a drawn-out row over the proposals surrounding the overall project but also the felling of two trees in Tittybottle Park as part of it, which prompted a campaign and protest to save them before they were taken down.
A signed road diversion route will be in place for the duration of the closures in the coming days, with pedestrians able to use the new temporary footbridge.
- Otley Bridge: 'do the right thing', group tells Leeds Council
- Work begins on the temporary bridge over the River Wharfe in Otley
- Work starts on installing new pedestrian bridge over River Wharfe in Otley
- Work begins to fell Otley oak tree after months of delays and protests
- Campaigners claim Leeds City Council is ‘misleading public’ over river bridge
For two weeks from Friday, May 30, 8pm to 5am, two-way traffic lights will be in place at Otley Bridge.
This is for the installation of the catenary system which will hold telecoms cables in place during main footway works.
Leeds City Council said, "while some disturbance and inconvenience are inevitable, the council will do its best to minimise disruption".
Councillor Jonathan Pryor, Leeds City Council’s deputy leader and executive member for economy, transport and sustainable development, said: "From Tuesday we’re able to open the temporary footbridge and I am delighted to see good progress is being made.
"This continues to be a complex and challenging project, so achieving this milestone to maintain pedestrian access across the river, marks significant success so far.
"This vital work will always involve some disruption and we will continue our best efforts to minimise any of this as much as possible.
"However, I know that it will still be inconvenient for people, and I would like to thank everyone for their understanding and patience so far whilst we do this urgent work.
"We will also continue to keep residents regularly updated as the works progress and work closely with our contractor, with an expected completion of the new Otley footbridge in the autumn."